What is the maximum test duration for any gas piping system regardless of its volume?

  1. 12 hours

  2. 36 hours

  3. 24 hours

  4. 8 hours

The correct answer is: 24 hours

The standard maximum test duration for any gas piping system, regardless of its volume, is established at 24 hours. This time frame allows for adequate monitoring to ensure that the system is airtight and that there are no leaks present. A 24-hour test is considered sufficient to observe any pressure drops that could indicate a leak while also allowing time for any potential pressure equalization to occur. Testing for a shorter duration may not provide enough assurance, as certain small leaks may take time to manifest in noticeable pressure changes. Conversely, extending the test beyond 24 hours may be unnecessary and potentially complicate the inspection process without yielding significant additional assurance of safety or leak-free integrity. Therefore, adhering to the 24-hour guideline is both practical and acknowledges the need for a balance between efficiency and thoroughness in ensuring the safety of gas piping systems.