For testing gas piping systems, which volume range requires a minimum testing time of 24 hours?

  1. Any volume greater than 10 cubic feet

  2. Any residential installation

  3. Any volume less than 10 cubic feet

  4. Only commercial systems over 100 cubic feet

The correct answer is: Any volume greater than 10 cubic feet

The minimum testing time of 24 hours for gas piping systems pertains to larger systems, particularly those with a volume greater than 10 cubic feet. This requirement is in place to ensure safety and reliability in the piping system. Larger systems may retain gas and potentially develop leaks over time, so a longer testing duration is crucial to observe any pressure drop that could indicate a leak. Smaller systems, like those under 10 cubic feet, may not require as extensive testing because they do not hold enough gas to present the same level of risk if a leak were to occur. Residential installations also vary in size, and while they may include larger systems that would fall under the 24-hour testing requirement, there is no blanket requirement for residential installations as a category. Similarly, the emphasis is not solely on commercial systems over 100 cubic feet, as the standard applies to any gas piping system exceeding the specified volume. Therefore, the focus on the volume greater than 10 cubic feet directly correlates to the need for a thorough testing protocol to safeguard against leaks and ensure the integrity of the gas system.