For piping with a volume greater than 10 cubic feet, how long should a pressure test be conducted?

  1. 1/2 hour per 100 cubic feet up to a maximum of 12 hours

  2. 1 hour per 500 cubic feet up to a maximum of 24 hours

  3. 1/2 hour per 500 cubic feet up to a maximum of 24 hours

  4. 15 minutes per 500 cubic feet up to a maximum of 12 hours

The correct answer is: 1/2 hour per 500 cubic feet up to a maximum of 24 hours

The correct response indicates that for piping with a volume greater than 10 cubic feet, a pressure test should be conducted for half an hour per 500 cubic feet, with a maximum duration of 24 hours. This approach is in line with standardized testing procedures to ensure that larger volumes allow for adequate detection of leaks and structural integrity. Conducting a pressure test is essential for ensuring the safety and reliability of gas piping systems. The specified duration provides a balance between sufficient time to observe potential leaks and practical testing limits. Testing times are often scaled with volume, as larger systems may take longer to stabilize and reveal any issues. The rationale behind the maximum testing duration also reflects the principle of minimizing delays while ensuring thoroughness, providing enough time for any pressure fluctuations to stabilize, which can help in accurately identifying leaks in larger systems. Proper adherence to these guidelines is crucial for compliance with safety regulations and for ensuring that the gas installation is safe for use.